South Florida East Coast Corridor Transit Analysis (SFECCTA)
Draft Project Schedule
  2005   2006 2007
Task S O N D J F M A M J J A S O N D J  
1. Project Management                                    
A. Notice To Proceed  
                             
                                     
2. Public Involvement                                    
A. Prepare and Submit Public Involvement Plan
 
                                 
B. Prepare and Submit Adv. Notification Package  
 
                               
C. Prepare and Conduct Scheduled Public Workshops, Meetings  
 
                               
D. Attend Unscheduled Public and Agency Meetings  
 
                               
E. Prepare and Maintain Project Website    
 
                             
F. Conduct Policy and Steering Committee Meetings  
 
                               
G. Conduct Business Group Meetings    
 
                             
H. Conduct Transportation Board Briefing Meetings    
 
     
 
     
 
             
                                     
3. Data Collection                                
 
 
A. Conduct Field Reviews  
 
                               
B. Submit Summary of Prior Studies Report  
 
                               
C. Conduct Interviews  
 
                               
D. Obtain Rdwy, Struct, Crash, Traf, Transit, Ports Data    
 
                             
E. Submit Existing Conditions Report        
 
                         
                                     
4. Develop Project Purpose, Needs                                    
A. Identify Transportation Deficiencies        
 
                         
B. Conduct Travel Surveys      
 
                           
C. Analyze Existing Pop, Emp, Trav. Patterns, Conditions          
 
                       
D. Submit Existing Trav. Characteristics Tech Memo                  
               
E. Submit Existing Transit Service Report            
                     
F. Submit Draft Purpose and Needs Report            
 
                     
G. Submit Travel Demand Methodology & Results Report                
             
 
 
                                     
5. Develop Regional Alternatives Analysis                                    
A. Define Initial Corridor Alternatives            
 
                     
B. Develop and Evaluate Freight Integration Alternatives    
 
                             
C. Submit Freight Integration Summary Report      
 
                           
D. Submit Conceptual Capital and O&M Cost Estimate Report                  
             
E. Submit Regional Tier 1 Screening Analysis Report                      
           
F. Prepare, Submit Regional Transit Analysis Summary Report                        
         
                                     
6. Develop Environmental Analysis and Reports                                    
A. Prepare, Submit Cultural Resource Analysis Report  
 
                               
B. Prepare, Submit Regional LandUse, Urban Design Issues Report      
               
         
C. Prepare, Submit Draft Tier 1 Environmental Impact Statement                    
 
           
D. Prepare, Submit Final Tier 1 Environmental Impact Statement                                
 
    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17